MCINNIS CEMENT TERMINAL EXPANSION

Located along the Providence River at the Port of Providence, RI the McInnis Cement Terminal was the first US Terminal for Canada based cement manufacturer, McInnis Cement. This cement terminal has the capacity to serve the New England Construction Market with its distribution of cement products to Rhode Island, Massachusetts, and Connecticut from this convenient terminal location. Manafort Brothers, Inc. was selected to perform the civil & utility as well as concrete scope of work for the expansion of this cement terminal.

Manafort’s civil & utility scope of work included structural excavation for new dome silo storage facility and associated support frames as well as site preparation for the new electrical equipment building and cement loadout structure. The dome silo measured 134 feet in diameter and has the capacity of storing 40,000 tons of cement.

 

In addition, Manafort performed the storm drainage upgrades, electrical service connection, and installed the new transformer pad for the cement terminal expansion. The site finishes included curbing, asphalt pavement, pavement markings, signage, and fencing. Manafort’s concrete scope of work included construction of cast in place concrete foundations for the new dome silo, electrical equipment building, and load-out structure.   

 

Manafort’s extensive civil and concrete work experience led to the safe, successful, on-time, and on-budget completion of this project.   

GARRAHY COURTHOUSE PARKING GARAGE

The Garrahy Courthouse Parking Garage project involved replacing an existing surface parking lot with a 7 tier, 1284 parking space garage in downtown Providence, RI adjacent to the Garrahy Courthouse. This parking structure included a basement level for Judge parking while the upper levels were intended for courthouse personnel and public parking. Manafort Brothers, Inc. was selected to perform the civil & utility work on this complex earthwork project.

Manafort’s civil scope of work included site demolition, design and installation of rammed aggregate pier and rigid inclusion ground improvements, design and installation of earth shoring, implementation of a complex dewatering system, mass excavation, soil disposal, structural excavation and backfill for the garage foundations, and grading for the slab on grade. The site finishes included asphalt pavement, concrete sidewalks, stamped concrete driveways, curbing, bollards, signage, and pavement markings.

 

Manafort’s utility scope of work included furnish and install of oil/water separators, sanitary sewer connections, storm drainage upgrades, domestic water and fire service connections, gas service, electrical and telecommunication duct banks, transformer pads, and site lighting.

 

The urban site constraints coupled with a high ground water table created logistical challenges that required diligent coordination and scheduling between Manafort and the Project Team. All work was performed safely, successfully, on-time, and on-budget.

 

YALE SCHWARZMAN CENTER

The Yale Schwarzman Center was a Yale University renovation project located in New Haven, CT, designed to provide a university-wide shared space to its community through restored spaces for student life to meet, dine, and collaborate. The project was constructed within and adjacent to the historical Yale University Commons, which first opened its doors in the early 1900’s. Manafort Brothers, Inc. was selected to perform the concrete, civil, and utility work for this complex renovation project that converted the original Yale University Commons to the Yale Schwarzman Center to fulfill Yale’s goal of unifying its student body.

Manafort’s civil & utility scope of work included site demolition, utility removal, pavement removal, new sanitary sewer connections, storm drainage upgrades, site lighting, electrical ductbanks, excavation and backfill for underslab utilities, support of existing utilities, structural excavation, support of excavation, construction dewatering, underpinning, interior excavation within the University Commons building, and site finishes.

 

Manafort’s concrete scope of work included structural walls, foundations, retaining walls, columns, piers, elevator pits, slabs on grade, slabs on deck, stairs, and miscellaneous flatwork.

 

The project was built on a small footprint with challenging site logistics in the heart of the Yale University campus requiring extensive scheduling, coordination, and management of vehicle and pedestrian traffic. The Manafort team’s experience working in tight urban locations, commitment to safety and quality, and familiarity with Yale University led to a safe, successful, on-time, and on-budget project completion.

HIGH STREET DAM REMOVAL AND BRIDGE REPLACEMENT

Located in Bridgewater, MA, the High Street Dam was rated as a Significant Hazard by the MA Office of Dam Safety for impeding migratory fish passage, interrupting natural river processes, and contributing to local flooding. Manafort Transit was selected to remove the existing 12 ft high and 80 ft wide dam across the Town River and replace the 170 year old High Street Bridge to withstand 500-year floods.

 

Manafort’s demolition scope included the design and installation of a temporary cofferdam, consisting of 3,000 lb sandbags, to temporarily divert and relocate Town River to facilitate the demolition of the existing dam and appurtenances under fully dewatered conditions. Manafort was required to selectively demolish and salvage portions of the historic dam for re-use on site.

Manafort’s bridge replacement scope included the construction of two new cast in place concrete bridge abutments and wingwalls supported by 3 ft diameter drilled shaft foundations. The new bridge superstructure included structural steel framing and a cast in place concrete deck. In addition, Manafort relocated gas, sanitary sewer, storm drainage, and water main utilities and constructed all site finishes on the project including reprofiling of the river channel, extensive river bank restoration, concrete sidewalks, and bituminous pavement.

 

The Manafort team’s extensive demolition and construction experience, in addition to close coordination with all project stakeholders and agencies, aided in the environmentally sound,  safe, successful , on-time, and on-budget completion of this project.