COPART RIVERFRONT BUSINESS PARK

image
  • PROJECT

    Copart Riverfront Business Park

  • MARKETS

    Civil & Utility

  • CONTRACT TYPE

    Specialty Contractor

  • PROJECT OWNER

    Copart of Connecticut, Inc.

  • LOCATION

    Freetown, MA

The Copart Riverfront Business Park project involved a 170 acre site development for the new car auction site located along the Taunton River in Freetown, MA. Due to the required stormwater management and sheer scale of the project footprint, this project was completed in two phases.  Manafort Brothers, Inc. was selected to perform Civil & Utility work for this substantial earthwork project.

Manafort’s scope of work included 600,000+ CY of earth moving operations, 178,000 CY of new Gravel Base for parking areas and roadways, 9,600 LF of Utility and Storm Drain Piping, 456,000 SY Chip Seal for parking areas and 30,000 SY of Bituminous Paving for office parking areas and haul roads.  In addition, the site finishes included drainage ponds, landscaping, curbing, concrete islands, fencing, signage, and pavement markings.  Manafort’s utility scope of work included domestic and fire service connections, gas service, sanitary sewer force mains, and site lighting.

 

Manafort utilized drone technology to analyze cut & fill areas throughout the site and GPS Technology on the earth moving equipment for maximum site development efficiency to ensure the project was completed safely, successfully, on-time, and on-budget.